Construction Notice - Noel Avenue Upgrading Project

Pritchard Road to Torrence Road


Beginning June 10, 2019 through September 20, 2019 construction crews will be upgrading road, sidewalk and and utilities along Noel Avenue from Pritchard Road to Torrence Road. Non-local traffic, pedestrians and cyclists are encouraged to use alternate routes to avoid delays.

Local residents and service providers will experience delays and single lane alternating traffic Monday to Friday (and possibly some Saturdays) between 7:00 am and 6:00 pm.

Emergency services will have unrestricted access through the site at all times.

Motorists, cyclists and pedestrians are encouraged to allow extra time, exercise caution and observe directions given by traffic control personnel.

Please direct all construction and traffic related inquires to: